Penetrating North South of the city of Sfax
The planned road will be developed into 2x2 lanes with a TPC and BAU on both sides in the open countryside and sidewalks in urban areas. The length is 13.3 km.
The section to be developed begins at the level of the existing roundabout, fitted out as part of the extension works of the ring road km11 and ends at the level of the junction projected at the exit of Taparura at the level of the north shore of the port of Sfax.
The mission concerns the Control, Monitoring and Technical Assistance of the work of lot N ° 3, namely:
- Earthworks and pavement;
- Drainage;
- Hydraulic and drainage works;
- Development of 7 roundabouts;
- Signage and safety equipment;
- Lighting ;
- Landscaping.
Services performed
Control, monitoring and technical assistance mission
Ministry of Equipment, Housing and Regional Planning
General Directorate of Bridges and Roads - DGPC
Project cost
53 182 963 TND INCLUDING TAX
FundingThe European Investment Bank and the Tunisian Government