The structure crosses the Meliane River, located on the axis of the RN3 national road which connects the capital Tunis (to the northeast) to the Algerian-Tunisian border (to the southwest).

The structure is a reinforced concrete girder bridge with three independent 24m. Each span is made up of 8 prefabricated variable-section I-beams connected by a 20 cm thick slab cast on site by means of a permanent formwork (B.A slabs 5 cm thick). The 10.86 m wide apron supports two –way traffic; It has two (2) end joints of the roadway.

The total structure length is 75.90 m.

It is a girder bridge with three (3) independent 24m spans.

Services performed

Execution design

Country

Tunisia

Client

Société Bouzguenda Frères (SBF)

Date