Road safety works on the RN1 between Pk 10 + 760 and 14 + 900 in the governorate of Ben Arous
The mission contributes to the improvement of travel conditions and the safety of citizens in Greater Tunis and to ensure better traffic flow on one of the structuring axes.
The objective of the mission is to develop eecution design for the development of the national road RN1 from PK10 + 760 to PK14 + 900 and construction works of three concrete `` urban viaduct '' structures. prestressed (respective lengths of 267m, 450m and 590m) and a reinforced concrete pedestrian bridge 40m in length.
Services performed
Execution design
Country
Client
Entreprise Afrique Travaux
DateProject cost
14 350 000 €
FundingEuropean Investment Bank